Works comprise new foundation pads, oil containment tank / drainage and extending the existing switchyard.
Connell Contractors is pleased to procure our first project directly contracting to Mitton Electronet.
Works will interface with a separate contract for the Lines Company.
Progress (October 2018)
Extensive works have been completed on this Transpower asset including switchyard extension, foundation pads constructed, oil separator installed and security fencing being erected.
Works are scheduled to be completed in the next few weeks. The follow-up project, working on The Lines Company asset, commenced in early November 2018.