Installation of five pump stations, together with gravity sewer and rising main pipework up to 700mm in diameter.
Two layers of wellpoints were required on most pump stations, to a depth of 6-8 metres with the water table at times of 1 metre below the surface.
Installation of five pump stations, together with gravity sewer and rising main pipework up to 700mm in diameter.
Two layers of wellpoints were required on most pump stations, to a depth of 6-8 metres with the water table at times of 1 metre below the surface.